3-2 Replacement of Bobbin- Page 42

Brother BE-0901E-AC-PC User Manual

2014 Dodge Charger SRT Owner Manual

Table of Contents

Chapter 6 Embroidering
background image

2-14

BE-0901E-AC-PC• BE-1201B-AC-PC

Chapter 2 Preparation of Embroidery Machine

1. Open the rotary hook cover [1].

2. Hold the knob [2] and take out the bobbin

case.

3. Close the knob and take out the bobbin [3].

1. Put a new bobbin in the bobbin case.

Check the winding direction. (refer the figure)
If the bobbin is inserted in the reverse
direction, the lower thread may slip too much,
resultingin a problem in embroidering.
Check that the bobbin is pushed out of the
bobbin case by about 0.5 mm. If not, the slip
prevention spring of the bobbin case does not
work. Adjust the height of the spring or
replace it with a new one.

W1580

2. Slide the thread under the tension spring [5]

through the notch [4].

3. Pull out the thread from the hole of the

tension spring [5].

4. Pull out the thread by about 50 mm.

3-2 Replacement of Bobbin

Note) Remove dust, lint and oil from the bobbin case before replacement.

!

!

!

!

 Removing bobbin case

W1576

!

!

!

!

 Replacing bobbin

W1238Q

W1577

W1238Q

W1578

W1238Q

W1579

 [1]

 [2]

 [3]

 [5]

[4]

Pull out by

about 50 mm

 [6]

0.5mm

Bobbin

Detailed Information for Brother BE-0901E-AC-PC User Manual

Lists of information found in Brother BE-0901E-AC-PC User Manual - Page 42

  • 1. Open the rotary hook cover [1].
  • 2. Hold the knob [2] and take out the bobbin case.
  • 3. Close the knob and take out the bobbin [3].
  • 1. Put a new bobbin in the bobbin case.
  • 2. Slide the thread under the tension spring [5] through the notch [4].
  • 3. Pull out the thread from the hole of the tension spring [5].
  • 4. Pull out the thread by about 50 mm.
  • BE-1201B-AC-PC Chapter 2 Preparation of Embroidery Machine 1.

Related Documents for Brother BE-0901E-AC-PC User Manual